Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia Class D PVC pipe 50 mm dia (Class D) PVC pipe | 1 | meter | 178 | meter | 178 | 178 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 36.67 | 36.67 | |
| Sub-Total | 214.67 | |||||||
| Contractor's Profit | 10% | 0.1 | 21.47 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 7.51 | |||||
| Total | 243.65 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 19.76 | ||||
| Grand Total | 263.41 | |||||||
| Rate per meter | 263 | |||||||
| Rate per meter | 263 | |||||||