Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 125 mm dia PVC housing pipe Class E 125 mm dia (Class E) PVC housing pipe | 1 | meter | 1192 | meter | 1192 | 1192 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1236 | |||||||
| Contractor's Profit | 10% | 0.1 | 123.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 43.26 | |||||
| Total | 1402.86 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 113.75 | ||||
| Grand Total | 1516.61 | |||||||
| Rate per meter | 1517 | |||||||
| Rate per meter | 1517 | |||||||