Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Grade 400/420(400Mpa / 400N/mm2 ≈ 60900psi/ 60 Grade), BDS-6935-2006, B400: and ratio fy to fu => 1.25 1 set centralizer consists of four leaves: 12 mm dia M.S. rod: 4 x 3'-0"+2*3.14*0.5=15'-3" | 9.1 | lbs | 72000 | per M. ton | 32.65 | 297.11 | |
| 2 | Ordinary labour Carriage, welding, fabrication and other necessary cost | 1 | LS | 550 | per day | 110 | 110 | |
| Sub-Total | 407.11 | |||||||
| Contractor's Profit | 10% | 0.1 | 40.71 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 14.25 | |||||
| Total | 462.07 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 37.47 | ||||
| Grand Total | 499.54 | |||||||
| Rate per each | 500 | |||||||
| Rate per each | 500 | |||||||