Considering a site of 5000 sft ground area
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Contractor's site office, store, stackyard, Labour shed, service connections, toilet facilities etc. cleaning site | 1 | LS | 550 | per day | 68750 | 68750 | |
| 2 | Ordinary labour Cleaning and removal | 1 | LS | 550 | per day | 13750 | 13750 | |
| Sub-Total | 82500 | |||||||
| Contractor's Profit | 10% | 0.1 | 8250 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2887.5 | |||||
| Total | 93637.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 7592.22 | ||||
| Grand Total | 101229.72 | |||||||
| Rate per sft | 20.25 | |||||||
| Rate per sqm | 217.97 | |||||||