Considering for 1 job
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm dia and 4 mm thick M.S. pipe 150 mm dia and 4 mm thick M.S. pipe | 1 | meter | 2550 | meter | 2550 | 2550 | |
| 2 | 4 mm thick 200 mm dia plate 4 mm thick 200 mm dia plate | 1 | no | 1240 | each | 1240 | 1240 | |
| 3 | Ordinary labour Welding and other cost as necessary | 1 | LS | 550 | per day | 550 | 550 | |
| Sub-Total | 4340 | |||||||
| Contractor's Profit | 10% | 0.1 | 434 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 151.9 | |||||
| Total | 4925.9 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 399.4 | ||||
| Grand Total | 5325.3 | |||||||
| Rate per each | 5325 | |||||||
| Rate per each | 5325 | |||||||