Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 75 mm dia Class D PVC pipe 75 mm dia Class D uPVC pipe | 1 | meter | 382 | meter | 382 | 382 | |
| 2 | Ordinary labour Cost of making slot and cleaning | 1 | meter | 550 | per day | 66 | 66 | |
| 3 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 492 | |||||||
| Contractor's Profit | 10% | 0.1 | 49.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 17.22 | |||||
| Total | 558.42 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 45.28 | ||||
| Grand Total | 603.7 | |||||||
| Rate per meter | 604 | |||||||
| Rate per meter | 604 | |||||||