considering 1 no.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Complete development of the tube-well up to 200 m depth. (75 mm x 150 mm tube-well) Development of tube well for depth up to 200 m. | 1 | LS | 33800 | LS | 33800 | 33800 | |
| Sub-Total | 33800 | |||||||
| Contractor's Profit | 10% | 0.1 | 3380 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1183 | |||||
| Total | 38363 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3110.51 | ||||
| Grand Total | 41473.51 | |||||||
| Rate per each | 41474 | |||||||
| Rate per each | 41474 | |||||||