Considering 72 hrs.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of pump including spare and maintenance Hire charge of pump in/c spare and maintenance | 72 | hrs | 320 | hour | 400 | 28800 | |
| 2 | Petrol Fuel for pump: @ 3.33 liter per hour | 240 | liter | 89 | litre | 89 | 21360 | |
| 3 | Foreman/Supervisor Foreman: @ 1 No. per 8 hrs | 9 | nos | 850 | per day | 850 | 7650 | |
| 4 | Skilled labour Skilled labour | 6 | nos | 600 | per day | 600 | 3600 | |
| 5 | Ordinary labour Local carriage, T & P | 1 | LS | 550 | per day | 1375 | 1375 | |
| Sub-Total | 62785 | |||||||
| Contractor's Profit | 10% | 0.1 | 6278.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2197.48 | |||||
| Total | 71260.98 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5777.91 | ||||
| Grand Total | 77038.89 | |||||||
| Rate per hour | 1069.99 | |||||||
| Rate per hour | 1069.99 | |||||||