Considering for 1 job
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 200 mm dia and 6 mm thick M.S. pipe welded 200 mm dia and 5 mm thick M.S. pipe | 1 | meter | 3600 | meter | 3600 | 3600 | |
| 2 | 5 mm thick 250 mm dia plate 5 mm thick 250 mm dia plate | 1 | no | 1400 | each | 1400 | 1400 | |
| 3 | Ordinary labour Welding and other cost as necessary | 1 | LS | 550 | per day | 825 | 825 | |
| Sub-Total | 5825 | |||||||
| Contractor's Profit | 10% | 0.1 | 582.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 203.88 | |||||
| Total | 6611.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 536.06 | ||||
| Grand Total | 7147.44 | |||||||
| Rate per each | 7147 | |||||||
| Rate per each | 7147 | |||||||