Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia PVC cap 100 mm dia uPVC cap | 1 | no | 400 | each | 400 | 400 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 444 | |||||||
| Contractor's Profit | 10% | 0.1 | 44.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 15.54 | |||||
| Total | 503.94 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 40.86 | ||||
| Grand Total | 544.8 | |||||||
| Rate per each | 545 | |||||||
| Rate per each | 545 | |||||||