Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia Class D PVC pipe 100 mm dia Class D uPVC pipe | 1 | meter | 531 | meter | 531 | 531 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 575 | |||||||
| Contractor's Profit | 10% | 0.1 | 57.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 20.13 | |||||
| Total | 652.63 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 52.92 | ||||
| Grand Total | 705.55 | |||||||
| Rate per meter | 706 | |||||||
| Rate per meter | 706 | |||||||