Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia Class E PVC pipe 100 mm dia Class E uPVC pipe | 1 | meter | 791 | meter | 791 | 791 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 835 | |||||||
| Contractor's Profit | 10% | 0.1 | 83.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 29.23 | |||||
| Total | 947.73 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 76.84 | ||||
| Grand Total | 1024.57 | |||||||
| Rate per meter | 1025 | |||||||
| Rate per meter | 1025 | |||||||