Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia Class D PVC pipe 100 mm dia Class D uPVC pipe strainer | 1 | meter | 531 | meter | 531 | 531 | |
| 2 | Ordinary labour Making slot and cleaning | 1 | meter | 550 | per day | 66 | 66 | |
| 3 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 641 | |||||||
| Contractor's Profit | 10% | 0.1 | 64.1 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 22.44 | |||||
| Total | 727.54 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 58.99 | ||||
| Grand Total | 786.53 | |||||||
| Rate per meter | 787 | |||||||
| Rate per meter | 787 | |||||||