Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia Class E PVC pipe 100 mm dia Class E uPVC pipe strainer | 1 | meter | 791 | meter | 791 | 791 | |
| 2 | Ordinary labour Making slot and cleaning | 1 | meter | 550 | per day | 66 | 66 | |
| 3 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 901 | |||||||
| Contractor's Profit | 10% | 0.1 | 90.1 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 31.54 | |||||
| Total | 1022.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 82.92 | ||||
| Grand Total | 1105.56 | |||||||
| Rate per meter | 1106 | |||||||
| Rate per meter | 1106 | |||||||