Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 200 mm dia PVC housing pipe Class D 200 mm dia Class D uPVC housing pipe | 1 | meter | 2548 | meter | 2548 | 2548 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 2592 | |||||||
| Contractor's Profit | 10% | 0.1 | 259.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 90.72 | |||||
| Total | 2941.92 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 238.53 | ||||
| Grand Total | 3180.45 | |||||||
| Rate per meter | 3180 | |||||||
| Rate per meter | 3180 | |||||||