Breakup

Filling of the borehole around the tube-well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay free from any substances harmful to pipes and health as per standard specification and accepted by the Engineer-in-charge.

Considering 100 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Foreman/Supervisor Foreman 1 no 850 per day 850 850
2 Skilled labour Skilled labour 6 nos 600 per day 600 3600
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 550 550
Sub-Total 5000
Contractor's Profit 10% 0.1 500
Contractor's Overhead Expenses 3.5% 0.035 175
Total 5675
Add VAT with adjustment factor. 1.08108 7.5% 0.075 460.13
Grand Total 6135.13
Rate per meter 61.35
Rate per meter 61.35