Considering 100 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Foreman/Supervisor Foreman | 1 | no | 850 | per day | 850 | 850 | |
| 2 | Skilled labour Skilled labour | 6 | nos | 600 | per day | 600 | 3600 | |
| 3 | Ordinary labour Local carriage, T & P | 1 | LS | 550 | per day | 550 | 550 | |
| Sub-Total | 5000 | |||||||
| Contractor's Profit | 10% | 0.1 | 500 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 175 | |||||
| Total | 5675 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 460.13 | ||||
| Grand Total | 6135.13 | |||||||
| Rate per meter | 61.35 | |||||||
| Rate per meter | 61.35 | |||||||