Considering for 1 job
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (i) 300 mm dia 6 mm thick M.S. housing pipe welded 300 mm dia and 6 mm thick M.S. pipe | 1 | meter | 5994 | meter | 5994 | 5994 | |
| 2 | 350 mm dia 6 mm thick M.S. cap 6 mm thick 350 mm dia plate | 1 | no | 2200 | each | 2200 | 2200 | |
| 3 | Ordinary labour Welding and other cost as necessary | 1 | LS | 550 | per day | 1375 | 1375 | |
| Sub-Total | 9569 | |||||||
| Contractor's Profit | 10% | 0.1 | 956.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 334.92 | |||||
| Total | 10860.82 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 880.61 | ||||
| Grand Total | 11741.43 | |||||||
| Rate per each | 11741 | |||||||
| Rate per each | 11741 | |||||||