Considering 0 m to 50 m
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 600 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks | 50 | meter | 1120 | meter | 1120 | 56000 | |
| Sub-Total | 56000 | |||||||
| Contractor's Profit | 10% | 0.1 | 5600 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1960 | |||||
| Total | 63560 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5153.51 | ||||
| Grand Total | 68713.51 | |||||||
| Rate per meter | 1374.28 | |||||||
| Rate per meter | 1374.28 | |||||||