Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm dia PVC cap 150 mm dia uPVC cap | 1 | no | 888 | each | 888 | 888 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 932 | |||||||
| Contractor's Profit | 10% | 0.1 | 93.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 32.62 | |||||
| Total | 1057.82 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 85.77 | ||||
| Grand Total | 1143.59 | |||||||
| Rate per each | 1144 | |||||||
| Rate per each | 1144 | |||||||