Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm dia Class D PVC pipe 150 mm dia (Class D) uPVC pipe | 1 | meter | 1436 | meter | 1436 | 1436 | |
| 2 | Ordinary labour Making slot and cleaning | 1 | meter | 550 | per day | 82.5 | 82.5 | |
| 3 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1562.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 156.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 54.69 | |||||
| Total | 1773.44 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 143.79 | ||||
| Grand Total | 1917.23 | |||||||
| Rate per meter | 1917 | |||||||
| Rate per meter | 1917 | |||||||