Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 200 mm dia PVC housing pipe Class E 200 mm dia Class-E | 1 | meter | 3074 | meter | 3074 | 3074 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 3118 | |||||||
| Contractor's Profit | 10% | 0.1 | 311.8 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 109.13 | |||||
| Total | 3538.93 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 286.94 | ||||
| Grand Total | 3825.87 | |||||||
| Rate per meter | 3826 | |||||||
| Rate per meter | 3826 | |||||||