Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 250 mm dia PVC housing pipe Class D 250 mm dia Class-D uPVC housing pipe | 1 | meter | 3550 | meter | 3550 | 3550 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 3594 | |||||||
| Contractor's Profit | 10% | 0.1 | 359.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 125.79 | |||||
| Total | 4079.19 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 330.74 | ||||
| Grand Total | 4409.93 | |||||||
| Rate per meter | 4410 | |||||||
| Rate per meter | 4410 | |||||||