considering no. 1\
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Complete development of the tube-well up to 200 m depth. (150 mm x 200 mm tube-well) Development of tube well for depth up to 200 m. | 1 | LS | 49600 | LS | 49600 | 49600 | |
| Sub-Total | 49600 | |||||||
| Contractor's Profit | 10% | 0.1 | 4960 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1736 | |||||
| Total | 56296 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 4564.54 | ||||
| Grand Total | 60860.54 | |||||||
| Rate per each | 60861 | |||||||
| Rate per each | 60861 | |||||||