Breakup

27.40 Filling of the borehole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay as free from any substances harmful to pipes and health per standard specification and accepted by the Engineer-in-charge.

Considering 100 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Foreman/Supervisor Foreman 1 no 850 per day 850 850
2 Skilled labour Skilled labour 9 no 600 per day 600 5400
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 687.5 687.5
Sub-Total 6937.5
Contractor's Profit 10% 0.1 693.75
Contractor's Overhead Expenses 3.5% 0.035 242.81
Total 7874.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 638.44
Grand Total 8512.5
Rate per meter 85.13
Rate per meter 85.13