27.42.1 From 0.0 m to 50 m = 50 m

Considering 0 m to 50 m

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 600 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 1120 meter 1120 56000
Sub-Total 56000
Contractor's Profit 10% 0.1 5600
Contractor's Overhead Expenses 3.5% 0.035 1960
Total 63560
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5153.51
Grand Total 68713.51
Rate per meter 1374.28
Rate per meter 1374.28