Breakup

05.6.2 With Pakistani chips In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 White Cement White cement 62.5 kg 27 per kg 27 1687.5
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Grey cement 1.25 bag 410 per bag 410 512.5
3 Pakistan origin (onix) mosaic chips Pakistani Onix mosaic chips 125 kg 20 per kg 20 2500
4 Minar stone for finishing mosaic work Minar stone 0.333333 no 420 each 420 140
5 1/2 " thick plaster (1:4) 1/2" thick plaster (1:4) 100 sft 23.22 sft 23.22 2322
6 Head mason / Mosaic head mistry Head mason 1 no 800 per day 800 800
7 Skilled labour Skilled labour 0.75 no 600 per day 600 450
8 Ordinary labour Ordinary labour 1 no 550 per day 550 550
9 Skilled labour Skilled labour 10 nos 600 per day 600 6000
10 Pumice stone for finishing mosaic work pumice stone 2.5 nos 175 each 175 437.5
11 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 15949.5
Contractor's Profit 10% 0.1 1594.95
Contractor's Overhead Expenses 3.5% 0.035 558.23
Total 18102.68
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1467.78
Grand Total 19570.46
Rate per sft 195.7
Rate per sqm 2106.51