Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (ii) 300 mm dia 6 mm thick M.S. housing pipe seamless 300 mm dia 6 mm thick M.S. housing pipe | 1 | meter | 8250 | meter | 8250 | 8250 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 8525 | |||||||
| Contractor's Profit | 10% | 0.1 | 852.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 298.38 | |||||
| Total | 9675.88 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 784.53 | ||||
| Grand Total | 10460.41 | |||||||
| Rate per meter | 10460 | |||||||
| Rate per meter | 10460 | |||||||