27.45.1 Wells up to 200 m depth

considering no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Complete development of the tube-well up to 200 m depth. (150 mm x 200 mm tube-well) vDevelopment of tube well for depth up to 200 m. 1 LS 49600 LS 49600 49600
Sub-Total 49600
Contractor's Profit 10% 0.1 4960
Contractor's Overhead Expenses 3.5% 0.035 1736
Total 56296
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4564.54
Grand Total 60860.54
Rate per each 60861
Rate per each 60861