Breakup

05.6.3 With Indian chips using 100% grey cement In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Grey cement 2.5 bag 410 per bag 410 1025
2 Indian origin (deradun) mosaic chips Indian deradun mosaic chips 125 kg 18 per kg 18 2250
3 Minar stone for finishing mosaic work Minar stone 0.333333 no 420 each 420 140
4 1/2 " thick plaster (1:4) 1/2" thick plaster (1:4) 100 sft 23.22 sft 23.22 2322
5 Head mason / Mosaic head mistry Head mason 1 no 800 per day 800 800
6 Skilled labour Skilled labour 0.75 no 600 per day 600 450
7 Ordinary labour Ordinary labour 1 no 550 per day 550 550
8 Skilled labour Skilled labour 10 nos 600 per day 600 6000
9 Pumice stone for finishing mosaic work pumice stone 2.5 nos 175 each 175 437.5
10 Ordinary labour Ordinary labour 1 no 550 per day 550 550
Sub-Total 14524.5
Contractor's Profit 10% 0.1 1452.45
Contractor's Overhead Expenses 3.5% 0.035 508.36
Total 16485.31
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1336.65
Grand Total 17821.96
Rate per sft 178.22
Rate per sqm 1918.36