Breakup

27.49.1 From 0.0 m to 50 m = 50 m

Considering 0 m to 50 m

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 800 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 1260 meter 1260 63000
Sub-Total 63000
Contractor's Profit 10% 0.1 6300
Contractor's Overhead Expenses 3.5% 0.035 2205
Total 71505
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5797.7
Grand Total 77302.7
Rate per meter 1546.06
Rate per meter 1546.06