Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 6 mm thick 200 mm dia M.S. Cap 6 mm thick 200 mm dia M.S. cap | 1 | no | 1560 | each | 1560 | 1560 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1604 | |||||||
| Contractor's Profit | 10% | 0.1 | 160.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 56.14 | |||||
| Total | 1820.54 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 147.61 | ||||
| Grand Total | 1968.15 | |||||||
| Rate per each | 1968 | |||||||
| Rate per each | 1968 | |||||||