Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (iv) 400 mm dia 6 mm thick M.S. housing pipe seamless 400 mm dia 6 mm thick M.S. housing pipe | 1 | meter | 11550 | meter | 11550 | 11550 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 11825 | |||||||
| Contractor's Profit | 10% | 0.1 | 1182.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 413.88 | |||||
| Total | 13421.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1088.22 | ||||
| Grand Total | 14509.6 | |||||||
| Rate per meter | 14510 | |||||||
| Rate per meter | 14510 | |||||||