Breakup

Complete installation of 200 mm dia deep tube well fixtures such as expanded top pipes, reducer, and tube well pipes, strainer, blind pipe. pipe cap etc. Fitting and fixing socket, welding and additional welding with fibre and placing in position with proper size M.S. centralizer @ 3 meter c/c in strainer position including blind pipe etc. complete as per standard practice and accepted by the Engineer-in-charge.

Considering 107 meter of 1 No. tube-well:

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Filling the pit with slurry in/c preparation of slurry 1 LS 550 per day 3666.67 3666.67
2 Ordinary labour Lowering the bail plug, strainer, 150 mm dia G.I. pipe and 300 mm dia M.S. housing pipe in/c coverage of risk 107 meter 550 per day 220 23540
3 Ordinary labour Verticality test 2 times 550 per day 3300 6600
4 Ordinary labour Necessary welding, cutting, jointing, levelling in/c cost of electrodes, welding set, electricity connection fees, tools and plants etc. 1 LS 550 per day 18150 18150
5 Ordinary labour Cost for filling the peagravels 28 cum 550 per day 97.08 2718.24
6 Ordinary labour Final anchoring the tubewell in/c supply of joint, concrete, brick work etc. 1 LS 550 per day 22000 22000
Sub-Total 76674.91
Contractor's Profit 10% 0.1 7667.49
Contractor's Overhead Expenses 3.5% 0.035 2683.62
Total 87026.02
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7056.16
Grand Total 94082.18
Rate per meter 879.27
Rate per meter 879.27
Help