Breakup

27.52.1 Wells up to 200 m depth

considering no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Complete development of the tube-well up to 200 m depth. (400 mm x 200 mm tube-well) Development of tube well for depth up to 200 m. 1 LS 47100 LS 47100 47100
Sub-Total 47100
Contractor's Profit 10% 0.1 4710
Contractor's Overhead Expenses 3.5% 0.035 1648.5
Total 53458.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4334.47
Grand Total 57792.97
Rate per each 57793
Rate per each 57793