considering no. 1
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Disinfections of tube-well using bleaching powder (for 50 mm x 125 mm tube-well) Cost for disinfection of the tube well including supply of all the materials and other necessary cost as per specification | 1 | LS | 1340 | LS | 2680 | 2680 | |
| Sub-Total | 2680 | |||||||
| Contractor's Profit | 10% | 0.1 | 268 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 93.8 | |||||
| Total | 3041.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 246.63 | ||||
| Grand Total | 3288.43 | |||||||
| Rate per each | 3288 | |||||||
| Rate per each | 3288 | |||||||