Breakup

05.7.2 With Pakistani chips and glass strip In ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 White Cement White cement 125 kg 27 per kg 27 3375
2 Pakistan origin (onix) mosaic chips Pakistani onix mosaic chips 125 kg 20 per kg 20 2500
3 Minar stone for finishing mosaic work Minar stone 0.333333 no 420 each 420 140
4 20 mm x 50 mm glass strip 5 x 20 mm glass strip 120 rft 10 per foot 10 1200
5 25 mm thick patent stone (1:2:4) with brick/chips for mosaic work Cost of patent stone excluding cost of cement for neat finish and 1/4 No. mason 100 sft 3307.74 % sft 33.08 3308
6 Head mason / Mosaic head mistry Head mason 0.75 no 800 per day 800 600
7 Skilled labour Skilled labour 0.75 no 600 per day 600 450
8 Ordinary labour Ordinary labour 1 no 550 per day 550 550
9 Mason / Mosaic mistry Mason 0.75 no 700 per day 700 525
10 Ordinary labour Ordinary labour 0.75 no 550 per day 550 412.5
11 Hire charge of mosaic cutting machine Hire charge in/c meter setting and electricity cost. 1 day 550 per day 550 550
12 Machine operator Machine operator 1 no 700 per day 700 700
13 Skilled labour Helper/Skilled labour 1 no 600 per day 600 600
14 Ordinary labour Ordinary labour 1 no 550 per day 550 550
15 Pumice stone for finishing mosaic work pumice stone 3 nos 175 each 175 525
16 Ordinary labour Ordinary labour 1 no 550 per day 550 550
17 Colour pigment Add for colour pigment 8 lbs 80 per lbs 80 640
Sub-Total 17175.5
Contractor's Profit 10% 0.1 1717.55
Contractor's Overhead Expenses 3.5% 0.035 601.14
Total 19494.19
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1580.61
Grand Total 21074.8
Rate per sft 210.75
Rate per sqm 2268.51