Breakup

27.56.1 From 0.0 m to 50 m = 50 m

Considering 0 m to 50 m

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 325 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 780 meter 780 39000
Sub-Total 39000
Contractor's Profit 10% 0.1 3900
Contractor's Overhead Expenses 3.5% 0.035 1365
Total 44265
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3589.05
Grand Total 47854.05
Rate per meter 957.08
Rate per meter 957.08