Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia GI pipe 50 mm dia 4.85 mm thick G.I. pipe | 1 | meter | 250 | per foot | 820.25 | 820.25 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| Sub-Total | 957.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 95.78 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33.52 | |||||
| Total | 1087.05 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 88.14 | ||||
| Grand Total | 1175.19 | |||||||
| Rate per meter | 1175 | |||||||
| Rate per meter | 1175 | |||||||