Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm dia 6 mm thick M.S. housing pipe seamless 150 mm dia 6 mm thick M.S. housing pipe | 1 | meter | 3850 | meter | 3850 | 3850 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 4125 | |||||||
| Contractor's Profit | 10% | 0.1 | 412.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 144.38 | |||||
| Total | 4681.88 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 379.61 | ||||
| Grand Total | 5061.49 | |||||||
| Rate per meter | 5061 | |||||||
| Rate per meter | 5061 | |||||||