Considering 72 hrs.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of pump including spare and maintenance Hire charge of pump in/c spare and maintenance | 72 | hrs | 320 | hour | 320 | 23040 | |
| 2 | Petrol Fuel for pump: @ 4.375 liter per hour | 315 | liter | 89 | litre | 89 | 28035 | |
| 3 | Foreman/Supervisor Foreman: @ 1 No. per 8 hrs | 9 | nos | 850 | per day | 850 | 7650 | |
| 4 | Skilled labour Skilled labour | 6 | nos | 600 | per day | 600 | 3600 | |
| 5 | Ordinary labour Local carriage, T & P | 1 | LS | 550 | per day | 935 | 935 | |
| Sub-Total | 63260 | |||||||
| Contractor's Profit | 10% | 0.1 | 6326 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2214.1 | |||||
| Total | 71800.1 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5821.62 | ||||
| Grand Total | 77621.72 | |||||||
| Rate per hour | 1078.08 | |||||||
| Rate per hour | 1078.08 | |||||||