Breakup

Filling of the borehole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay free from any substances harmful to pipes and health as per standard specification and accepted by the Engineer-in-charge.

Considering 100 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Foreman/Supervisor Foreman 1 no 850 per day 850 850
2 Skilled labour Skilled labour 4 nos 600 per day 600 2400
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 687.5 687.5
Sub-Total 3937.5
Contractor's Profit 10% 0.1 393.75
Contractor's Overhead Expenses 3.5% 0.035 137.81
Total 4469.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 362.36
Grand Total 4831.42
Rate per meter 48.31
Rate per meter 48.31
Help