Breakup

27.63.1 From 0.0 m to 50 m = 50 m

Considering 0 m to 50 m

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 350 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 850 meter 850 42500
Sub-Total 42500
Contractor's Profit 10% 0.1 4250
Contractor's Overhead Expenses 3.5% 0.035 1487.5
Total 48237.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3911.14
Grand Total 52148.64
Rate per meter 1042.98
Rate per meter 1042.98