Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 75 mm dia GI pipe 75 mm dia 4.85 mm thick G.I. pipe | 1 | meter | 416 | per foot | 1364.9 | 1364.9 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1408.9 | |||||||
| Contractor's Profit | 10% | 0.1 | 140.89 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 49.31 | |||||
| Total | 1599.1 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 129.66 | ||||
| Grand Total | 1728.76 | |||||||
| Rate per meter | 1729 | |||||||
| Rate per meter | 1729 | |||||||