Breakup

27.66.1 Wells up to 200 m depth

considering no. 1

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Complete development of the tube-well up to 200 m depth. (75 mm x 150 mm tube-well) Development of tube well for depth up to 200 m. 1 LS 33800 LS 33800 33800
Sub-Total 33800
Contractor's Profit 10% 0.1 3380
Contractor's Overhead Expenses 3.5% 0.035 1183
Total 38363
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3110.51
Grand Total 41473.51
Rate per each 41474
Rate per each 41474
Help