Breakup

Filling of the borehole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay free from any substances harmful to pipes and health as per standard specification and accepted by the Engineer-in-charge.

Considering 100 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Foreman/Supervisor Foreman 1 no 850 per day 850 850
2 Skilled labour Skilled labour 5 nos 600 per day 600 3000
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 687.5 687.5
Sub-Total 4537.5
Contractor's Profit 10% 0.1 453.75
Contractor's Overhead Expenses 3.5% 0.035 158.81
Total 5150.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 417.57
Grand Total 5567.63
Rate per meter 55.68
Rate per meter 55.68