Breakup

27.70.1 From 0.0 m to 50 m = 50 m

Considering 0 m to 50 m

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 400 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 890 meter 890 44500
Sub-Total 44500
Contractor's Profit 10% 0.1 4450
Contractor's Overhead Expenses 3.5% 0.035 1557.5
Total 50507.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4095.2
Grand Total 54602.7
Rate per meter 1092.06
Rate per meter 1092.06