Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm dia G.I. pipe 100 mm dia 6 mm thick G.I. pipe | 1 | meter | 603 | per foot | 1978.44 | 1978.44 | |
| 2 | Ordinary labour Carriage of materials | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| Sub-Total | 2115.94 | |||||||
| Contractor's Profit | 10% | 0.1 | 211.59 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 74.06 | |||||
| Total | 2401.59 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 194.72 | ||||
| Grand Total | 2596.31 | |||||||
| Rate per meter | 2596 | |||||||
| Rate per meter | 2596 | |||||||