Breakup

Complete installation of 100 mm dia deep tube-well fixtures such as expanded top pipes, reducer, and tube-well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing socket, welding and additional welding with fibre and placing in position with proper size M.S. centralizer @ 3 meter c/c in strainer portion including blind pipe etc. complete as per standard practice and accepted by the Engineer-in-charge

Considering 107 meter of 1 No. tube-well:

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Filling the pit with slurry in/c preparation of slurry 1 LS 550 per day 3666.67 3666.67
2 Ordinary labour Lowering the bail plug, strainer, 50 mm dia G.I. pipe and 150 mm dia M.S. housing pipe in/c coverage of risk 107 meter 550 per day 220 23540
Sub-Total 27206.67
Contractor's Profit 10% 0.1 2720.67
Contractor's Overhead Expenses 3.5% 0.035 952.23
Total 30879.57
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2503.75
Grand Total 33383.32
Rate per meter 311.99
Rate per meter 311.99