Considering 107 meter of 1 No. tube-well:
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Filling the pit with slurry in/c preparation of slurry | 1 | LS | 550 | per day | 3666.67 | 3666.67 | |
| 2 | Ordinary labour Lowering the bail plug, strainer, 50 mm dia G.I. pipe and 150 mm dia M.S. housing pipe in/c coverage of risk | 107 | meter | 550 | per day | 220 | 23540 | |
| Sub-Total | 27206.67 | |||||||
| Contractor's Profit | 10% | 0.1 | 2720.67 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 952.23 | |||||
| Total | 30879.57 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2503.75 | ||||
| Grand Total | 33383.32 | |||||||
| Rate per meter | 311.99 | |||||||
| Rate per meter | 311.99 | |||||||