Breakup

Filling of the borehole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawn selected soil or local clay free from any substances harmful to pipes and health as per standard specification and accepted by the Engineer-in-charge

Considering 100 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Foreman/Supervisor Foreman 1 no 850 per day 850 850
2 Skilled labour Skilled labour 6 nos 600 per day 600 3600
3 Ordinary labour Local carriage, T & P 1 LS 550 per day 687.5 687.5
Sub-Total 5137.5
Contractor's Profit 10% 0.1 513.75
Contractor's Overhead Expenses 3.5% 0.035 179.81
Total 5831.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 472.79
Grand Total 6303.85
Rate per meter 63.04
Rate per meter 63.04