Up to 60 m depth Considering 1 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 40 mm dia "D" grade pipe 40 mm dia uPVC pipe | 1 | rft | 40 | foot | 40 | 40 | |
| 2 | Ordinary labour Labour for sinking and other costs | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 95 | |||||||
| Contractor's Profit | 10% | 0.1 | 9.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.33 | |||||
| Total | 107.83 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 8.74 | ||||
| Grand Total | 116.57 | |||||||
| Rate per meter | 1.95 | |||||||
| Rate per meter | 1.95 | |||||||